波音游戏-波音娱乐城赌球打不开

Campus Network Upgrade: Phase I

by Dick Wong
 
 
A new upgrade of the campus network had already been started with Phase I (replace/upgrade the network switches at the core and distribution layers) being completed in 2015.
 
The existing network design adopted a traditional 3-tier hierarchical model comprising the core, distribution and access layers. The Phase I network upgrade immediately increased the campus core network switching capacity by 2.8 times, with ample upgrade potential to meet future demand. Full network redundancy was provided at the core and distribution layers such that switches at these layers could be replaced one by one with no service interruption.  Let us briefly describe the migration steps for these layers:
 
Upgrade one of the core switches
 
  1. Prepare to remove Core Switch 2. By adjusting Layer(L)3 link cost, all network traffic is diverted to Core Switch 1.
  2. Power down and dismantle Core Switch 2.
  3. Install new Core Switch 2.  Verify that it resumes fully and becomes operational again.
 
 
Upgrade distribution layer switches
 
Distribution switches were virtualized by using a technology called VSS (Virtual Switching System), with which a pair of physical switches could operate as a single logical virtual switch.  
 
  1. Prepare to remove Distribution Switch Y.   By adjusting L3 link cost and changing the priority of the Hot Standby Router Protocol (HSRP) per Virtual LAN (VLAN), e.g. Staff LAN, Student LAN, all L2/L3 network traffic is diverted to Distribution Switch X.
  2. Power down and dismantle Distribution Switch Y.
  3. Install new Distribution Switch Y in connection to new L2-core (VSS). Verify that it resumes fully and becomes operational again.
  4. Prepare to remove Distribution Switch X.   By adjusting L3 link cost and changing the priority of the Hot Standby Router Protocol (HSRP) per VLAN, all L2/L3 network traffic is diverted to Distribution Switch Y. Power down and dismantle Distribution Switch X.
  5. Install new Distribution Switch X and form VSS with Distribution Switch Y (renamed as Distribution Switch VSS-X).  Verify that it resumes fully and becomes operational again. 
Upgrade distribution Layer switches serving departmental router which supports Student LAN
 
  1. Setup dual L3 uplinks for departmental student LAN. Adjust L3 link cost so as to divert all network traffic to one of the L3 uplinks.
  2. Power down and dismantle Distribution Switch Y.
  3. Upgrade Distribution Layer Switch Y and verify that both L3 uplinks resume fully and become operational again. Adjust L3 link cost so as to divert all network traffic to the other L3 uplink.
  4. Power down and dismantle Distribution Switch X.
  5. Install and form new Distribution Switch VSS-X. Verify that both L3 uplinks resume fully and become operational again. 
Upgrade the remaining core switch
 
Replacement of the next remaining Layer-3 Core switch was initiated after the installation of all VSS Distribution switches were completed and tested.
 
  1. Prepare to remove Core Switch 1.  By adjusting L3 link cost, all network traffic is diverted to Core Switch 2.  Power down and dismantle Core Switch 1.
  2. Install new Core Switch 1.  Verify that it resumes fully and becomes operational again. 

     
Lessons learnt from Phase I
 
A lot of valuable lessons were learnt and experiences gained during the deployment process as some of the problems we had faced were unexpected.
 
  • Tight schedule
Owing to the prolonged tendering process, the main part of Phase I campus network upgrade has to be completed in a relatively short time (during the Summer Term of 2015) by a small core team who carried out most of the design and installation work.  To start the replacement of switches for the Phase I network upgrade, the health condition of each new switch for the core and distribution layers was closely monitored on the testing network first, and if satisfactory, it would then be installed one by one to replace the corresponding old switch, and was tested again in the production network.   Each additional new switch being installed and tested in the production network will increase correspondingly the complexity and the time for the testing.  With such tedious and repeated process, on average only 2 switches could be replaced per week, and we managed to replace all 16 switches (excluding the distribution layer for Wireless LAN and gateway) within two months.
  • Zero service downtime
To minimize the interruption, delay, suspension of access, or unavailability of network services, the core or distribution layer could not be totally shutdown for replacement.  Careful planning for diverting and resuming network traffic was critical to make the zero downtime possible.  We started with a comprehensive cost and role calculating for the different layers to divert network traffic away from those old switches to be replaced.  Although the upgrading process unavoidably had affected network traffic, we managed to control the change of traffic flow such that it caused no significant impact to network services.
  • Cabling work
Due to the changing of network interface adaptor of distribution layer switches (from SC to LC), over 300 fibre patch cables were replaced during the upgrade.   We managed to mobilize the extra manpower required for fibre cable re-testing.
  • Software bugs
Cisco IOS (Internetwork Operating System) for the new core and distribution switches had bugs such as high CPU, unable to collect resource information and configure UTP interface.  After reporting to the vendor, a new IOS version was officially released in Oct 2015 and fortunately it resolved all the major issues that CityU had encountered thus far during the new switches deployment.
 
Current status and future work
 

With the completion of Phase I of the network upgrade, it not only enhances the overall switching throughput of the backbone network, but also improves its resiliency, availability and stability.  The next phase of the network upgrade will begin in the coming summer whereby around 50% of the switches in the access layer will be replaced and selected new features will be implemented for this layer.

 

百家乐试玩活动| 百家乐官网庄6点| 星期八娱乐城官网| 百家乐官网娱乐网备用网址| 威尼斯人娱乐平台博彩投注平| 澳门百家乐官网娱乐开户| 百家乐做庄家必赢诀窍| 百家乐官网网上赌博| 百家乐园36bol在线| 申博娱乐城开户| 喜力百家乐官网的玩法技巧和规则 | 百家乐黏土筹码| 网上百家乐官网赌场娱乐网规则| 大发888老虎机平台| 顶级赌场官方安卓版手机下载| 678百家乐官网博彩赌场娱乐网规则| 大发888在线娱乐城二十一点| 百家乐官网玩牌| 大发888的示例| 百家乐破解赌戏玩| 淘金百家乐官网的玩法技巧和规则| 大发888娱乐场下载官方| 百家乐官网单机破解版| 打牌网| 迷你百家乐的玩法技巧和规则| 单机百家乐官网小游戏| 望江县| 贵族百家乐官网的玩法技巧和规则| 金冠娱乐城注册| 娱乐城百家乐送白菜| 百家乐官网游戏开发软件| 同花顺百家乐的玩法技巧和规则 | 新西兰百家乐官网的玩法技巧和规则| 翼城县| 威尼斯人娱乐城老品牌值得您信赖lm0| 24风水| 皇冠投注網| 百家乐下注法| 娱乐城百家乐可以代理吗 | 同乐成娱乐| 林周县|