Progress report on student hostels development

Theresa Fox

 

Dr Brian Mitchenere has crossed his fingers many times that a project will be finished on time and according to plan. So the Associate Director of Campus Planning can be excused for having his fingers and toes crossed these days, as the official completion date for Blocks I and II of Phase I of the student hostels project draws near. "The scaffolding is coming down and we're doing all we can to press the builder to be finished on time. But there's a saying in this business that with building contracts, if anything can go wrong, it always does."

The official completion date is 14 April, as the contractors were given extra time because of inclement weather. The Campus Planning Office (CPO) expects Blocks I and II to be completed by the end of April and Block III, which includes the multi-function hall, around the end of May, Dr Mitchenere said.

With the scaffolding coming down, work is progressing on the inside of the buildings. Already, much of the plastering work is completed, the lifts are installed, though not commissioned, and the internal finishing and building services are well under way. "The mock-up for the typical student room has been finished, including the soft furnishing--as has the mock-up of one of the flats in the essential staff quarters," Dr Mitchenere reported.

CPO is hoping to have all the soft furnishing installed by mid-June, which will give CityU staff time to familiarize themselves with the new buildings before the initial influx of students. A group of undergraduate students from Shanghai will be the first to experience hostel life on the CityU campus. They will move in at the beginning of August, followed by our own students at the end of August, in time for the new semester in September.

As for the later phases, Phase II suffered a setback when the contractor filed for court protection in Japan. This had a knock-on effect and worked stopped on the CityU site. The project has been re-tendered and CPO expects work will re-commence on site in early March and that Phase II will be completed by the original date of August 2003.
Tender documentation for Phase III is currently being compiled and the aim is to go to tender for that phase in March, Dr Mitchenere said.

For a live view of what's happening on Phase I, log on to www.jvrhmfr.xyz/cityu/about/view.htm.

 

YOU MAY BE INTERESTED

Contact Information

Communications and Institutional Research Office

Back to top
百家乐官网赌博详解| 百家乐出千工具价格| 都坊百家乐官网的玩法技巧和规则| 南充市| 大发888棋牌游戏下载| 视频百家乐平台| 将军百家乐的玩法技巧和规则| 百家乐庄和闲的赌法| 怎样玩百家乐赢钱| 免费百家乐官网追号软件| 王子百家乐官网的玩法技巧和规则| 电投百家乐官网网站| 金盾百家乐官网网址| 大赢家足球比分| 德兴市| 百家乐官网大小点桌子| 百家乐官网游戏教程| 网络百家乐官网的玩法技巧和规则| 开店做生意的风水| 百家乐投注助手| 网上百家乐作弊法| 状元百家乐的玩法技巧和规则 | 同乐城百家乐娱乐城| 威尼斯人娱乐网赌| 大发888大发娱乐场| 顶级赌场371betcwm| 中国足球竞猜| 澳门百家乐官网论谈| 扎兰屯市| 百家乐官网机械投注法| 真人百家乐官网赌场娱乐网规则 | 全讯网信息| bet365会员注册| 楚雄市| 百家乐官网赌场技巧论坛| 新彩百家乐官网的玩法技巧和规则| 百家乐官网大娱乐场开户注册| 试玩百家乐官网代理| 百家乐怎么赢对子| 威尼斯人娱乐场28gxpjwnsr| 博娱乐城|